Driftwood Pipeline

Line 200 and Line 300

Line 200 and Line 300

Our newly proposed pipeline project, Line 200 and Line 300, is a $1.28 billion approximately 37-mile-long dual 42-inch-diameter interstate natural gas pipeline project that will originate near Ragley in Beauregard Parish and end near Carlyss in Calcasieu Parish. The pipelines will provide potential Shippers enhanced access opportunities to Haynesville sourced gas directly via new regional infrastructure located near Texas Eastern and Transco Pipeline mainline compressor stations.  This interconnectivity will provide enhanced supply reliability to meet the current and projected growth of the industrial, petrochemical, manufacturing and LNG plants located in or around Lake Charles. The pipelines will be developed and executed in two phases. Phase one is Line 200 and Phase two is Line 300.

Line 200 – Phase 1

  • 36.9 miles of a 42-inch diameter pipeline
  • 1 compressor station
  • 11 interconnects
  • Approximately 2.4 Bcf/d of flowing gas

Line 300 – Phase 2

  • 32.4 miles of 42-inch diameter looping pipeline
  • Expansion of existing compressor station
  • Approximately 4.6 Bcf/d of flowing gas
Line 200 and Line 300 Map

NOTICE OF AVAILABILITY

Request for proposal for the preparation of a third-party prepared environmental impact statement for the DWPL Line 200 and Line 300 project | Proposals due October 6, 2021 by 12:00 p.m. CST.

VIRTUAL OPEN HOUSE AND IN-PERSON MEETINGS HAVE CONCLUDED

Virtual open house | This event took place on Feb. 10 from 5:00 p.m. – 6:00 p.m.
In-person meetings | These events occurred on Feb. 17 in Carlyss, LA and Feb. 18 in Ragley, LA.
Note: Due to weather, In-person meetings were rescheduled and took place on Feb. 24 in Carlyss, LA and Feb. 25 in Ragley, LA

NOTICE OF OPEN SEASON HAS CONCLUDED

Beginning of Binding Open Season
12:00 P.M. CST, Monday, March 29, 2021

Closing of Binding Open Season
4:00 P.M. CST, Friday, April 2, 2021

NOTICE OF OPEN SEASON HAS CONCLUDED

Beginning of Binding Open Season
12:00 P.M. CST, Tuesday, December 14, 2021

Closing of Binding Open Season
4:00 P.M. CST, Friday, January 14, 2022